Home General Bond Project Information Summary of Major
Bond Projects
Work Taking Place           


Information/Action taking place at
September 12, 2006,
Board of Education meeting

Funding Requisition
Bond Project Manager Mr. Maready requested the board approve a requisition for the Newport Elementary School 5th grade wing HVAC replacement in the amount of $80,937. The equipment in that wing failed prior to the opening of school. Instead of spending maintenance money on the project, which would be handled in the overall HVAC renovations as part of the bond work, it was decided to segregate that area and complete the work in order to provide cooling when school started.
Bill Blair made motion for the funding requisition for Newport Elementary School in the amount of $80,937 with a $3,000 contingency. Adele Collins provided the second and all members voted aye.
Mr. Maready said the only enhancement that remained would be the controls and perhaps some additional insulation after the overall HVAC work was completed.

Project Ordinance Amendment Requisitions
Mr. Maready requested the Board consider two Project Ordinance Amendment Requisitions. 
1 – The first Project Ordinance Amendment Requisition request was for the White Oak Elementary School gym roof replacement in the amount of $73,752.
2 – The second Project Ordinance Amendment Requisition was for the White Oak Elementary School gym HVAC work in the amount of $134,000. The system will feature packaged heat pumps with reheat coils for dehumidification and supplemental heat.
Adele Collins made the motion to approve the two project ordinance amendment requisitions for White Oak Elementary School as presented.
Bill Blair provided the second and all members voted aye.
The Project Ordinance Amendment Requisitions will be presented to the County Commissioners for consideration.
 

Update on Bond Projects
Mr. Maready updated the Board on the following bond projects:
Door renovation and window replacement scope of work development is complete. School system staff is reviewing the scope of work for compatibility with existing policy. Bids will be reviewed in late September and work should begin in late October.
The Beaufort Middle School roof replacement is in progress.
The Broad Creek Middle School roof replacement will begin this month.
The condition of White Oak Elementary School’s gym has been considered an emergency. Stanford White Associates (SWA) has provided the HVAC design and Roof Engineering, Inc. (REI) has provided the roof replacement design. Bids will be received by September 15 and work will begin as soon as possible.
SWA representatives and school system staff are preparing for a final review of the HVAC design on several bond projects.
REI will complete all preliminary roof designs by the end of the year.
SFL+a Architects will have design documents complete for Bogue Sound Elementary School and East Carteret High School by the end of November. Design documents for Newport Elementary School and White Oak Elementary School will be complete by the end of the year.
He also noted Morehead City Elementary School’s electrical and HVAC renovations are in progress and the roof replacement will begin in October.