BOND
PROJECTS Bond
Projects Manager Keith Maready asked Board members to formally request
the County Commissioners approve the sale of $18.3 of the bonds so funds
would be available by April 2007 for the new construction at East
Carteret High School and for additional projects scheduled after 2007. Mr.
Maready’s report noted to date the Board of Education has received
bids on approximately 6.4 percent of the $49,045,283 in bond projects.
Projects bid include HVAC, electrical, roofing, door renovations and
site work. He noted the projects are on schedule as presented and
approved by the Board of Education June 5, 2006. Mr.
Maready’s report noted the County has previously sold $22,000,000 of
the bond value, which will cover the projected spending through the
fourth quarter of 2007 with the exception of the new construction work
at East Carteret High School. The projected starting date for the new
construction at East Carteret High School is April 2007. County
Manager John Langdon said if there was a significant amount of money for
the renovation of East Carteret High School in the second bond sale
there were several issues that would need to be resolved by the Board of
Education before he believes the County Commissioners would be
comfortable selling the bonds. Dr.
Luettich said the request for the selling of the bonds was very closely
tied to decision process at East Carteret High School and to the
timeline for the project. He was reluctant to request the County
Commissioners to sell $18.3 million of the remaining bonds if needed
decisions had not been made by the Board of Education. Dr.
Luettich made the motion to table the request to sell $18.3 million of
the remaining bonds until action was taken by the Board of Education on
East Carteret High School’s renovation plan. This action would be
expected in December. David
Carr provided the second. Dr.
Luettich said until the Board of Education makes decisions about the
renovations at East Carteret High School it is not appropriate to
request the Commissioners sell bonds. He requested more information
about the renovations and could not make decisions until that
information was provided. The
motion failed 3-4 with June Fulcher, Bill Blair, Cathy Neagle and Al
Hill casting nay votes. Dr.
Luettich said what the Board of Education does at East Carteret High
School and when it does it has a substantial impact on the cash flow. June
Fulcher said the quicker this issue could be resolved the sooner the
work could proceed. She said a special meeting might be in order to get
the work moving forward. Attorney
Neil Whitford suggested a special meeting be called in two weeks. David
Carr made motion to instruct Superintendent Dr. David Lenker to schedule
a meeting within two weeks to act on the request of issuance of bonds
and on the approval of the East Carteret High School renovation project. RECEIVE
BOND PROJECTS UPDATE The
roofing projects at Broad Creek Middle School and Beaufort Middle School
are progressing well. He noted the projects are on schedule with no
discovery of unacceptable work in place. Pricing for heat and rust
treatment protection for two kitchen equipment exhaust vents at Broad
Creek Middle is being sought. Mr. Maready said the vents are causing
undesirable stains on the current shingle roof and would cause the same
on a new roof in short term. The soffit and fascia panels at Beaufort
Middle are being addressed in the roofing contract. As soffits are being
removed there is discovery of wall panels just below the soffit line
that are allowing air and possibly wind driven rain to enter the
building. Roofing Engineering Inc. (REI) is working with Mr. Maready to
seek ways to resolve the issue. Mr. Maready said the most cost effective
and efficient means is application of elastomeric water proofing, and he
has asked the contractor for a price. Work on
White Oak Elementary School’s gym roof and HVAC will begin at the end
of November. Contracts for the door renovation projects at the school
will be issued by the end of November, and the window renovations bid
evaluation will be complete by November 15. Mr.
Maready reported that all design work for bond projects is progressing
on schedule. |
||||||