Atlantic Elementary – The HVAC project is ongoing with acceptable
quality and progress.
Broad Creek Middle – A pre-bid conference for the HVAC project has
taken place and the bid date is set for mid-August. East
Carteret High – Contracts are prepared for the second phase of
window replace with an expected start date in mid-September. The roofing
project design should be completed in mid-August, with a bid date in
mid-September. Morehead City Middle – The window replacement project is starting and bid package preparation should be finalized by mid-August. Provided market conditions are favorable, Mr. Maready hopes to receive bids September 5. Morehead City Primary – Toilet partition replacement work is complete and final inspections will take place in the next week. Newport Elementary – The HVAC and new construction projects at this school are in progress and will be ongoing for the next 11 months. He noted the first footing pour has been made and the next one is planned for the coming week. The detention pond is in place and the piping is being put in place. Mr. Maready said the permanent safety fence will be in place around the pond by the end of the week. A roofing re-bid conference will take place later in August. Smyrna Elementary – The HVAC project is ongoing with acceptable quality and progress. Contracts are being prepared for the window replacement project with an expected start date in mid-September. West Carteret High – The lighting project for the softball field is complete and final inspections have been conducted.
White Oak Elementary – The HVAC project is in the start-up phase and
will be on-going for the next 12 months. The new construction project is
on hold awaiting permit resolution. Mr. Maready projects this will be
about a 30-day waiting period. Dr.
Rick Luettich asked what percentage of the bond projects were currently
under contract. |
||||||