Project planning for all bond projects has been completed and each
project has received an assigned value. This schedule / cash flow chart
was approved by the Board of Education and presented to the County
Commissioners. The schedule continues through the 4th quarter
of 2010. The scheduled includes 13 categories and 71 projects. - A few
projects have been bid in recent weeks with very satisfying results.
Those include the heating/ventilation air conditioning system at Broad
Creek Middle School, the track and tennis court at West Carteret High
track, the roofing at Beaufort Middle and the parking lot at East
Carteret High. All the bids came in under budget. -Planning
studies have started on several other projects such as window
replacement and exterior door upfit. - The
HVAC and roofing engineers continue to deliver plans for review by the
Carteret County School team and additional projects will be bid in the
near future. - The
Board of Education reached an agreement with SFL+a (Shuller Ferris
Lindstrom & Associates) to remain as the architectural firm for
several bond new construction projects. This new agreement reflects a
revised fee structure and the assignment of a new architect of record.
The design of the addition at Bogue Sound Elementary should be complete
by the end of the year and construction should start in early 2007. The
East Carteret High new classroom addition design should be complete by
March 2007 and construction should start by summer 2007. -
Although the work at Morehead City Elementary School is not part of the
bond referendum package, it does focus on school improvements. The work
at that school is being paid for by an interest free Qualified Zone
Academy Bond (QZAB). Bids have been received for the HVAC and roofing at
Morehead Elementary and both were under budget. The electrical bids for
this project will be received soon. |
||||||