Projects Manager Keith Maready provided the following update to members
of the Bond Advisory Committee on July 19, 2006: Construction
drawings have been received on most all of the heating ventilation/air
conditioning (HVAC) renovation projects listed in the bond. The review
and design completion will occur by the end of the year and the projects
will be bid out early next year. The roof replacement at Beaufort Middle is expected to begin by mid August. The roof replacement at Broad Creek Middle will be bid August 3, 2006, and a recommendation to award the work will be made to the Board of Education August 8, 2006. The
scope of work and specifications are being prepared for window
replacement and door renovations. Window replacement work is expected to
begin this fall starting at East Carteret High. East Carteret High is
the first school scheduled for window replacement. The window work at
that school will be broken down into three major projects. HVAC
renovations in the administration area at Broad Creek Middle have
started and will be complete prior to school starting. Work on the track
and tennis court at West Carteret High is in progress and should be
complete before school starts. |
||||||