Information/Action
taking place at July 11, 2006, Board of Education meeting
BOND PROJECTS
UPDATE
Bond Project Manager Keith Maready updated the Board on several
projects.
Consider Approval
of Bid for Beaufort Middle Roof Replacement
Mr. Maready
recommended the Board approve a roofing contract for Beaufort Middle
School with Curtis Construction in the amount of $648,075 and ask the
County Commissioners for an amendment to the project ordinance. Mr.
Maready noted the bond budget for the work is $993,756.
The Board decided to hear
other bids and vote on them all at once.
Consider Award of
Roofing, HVAC and Electrical Bids for Morehead City Elementary School
The improvements at Morehead City Elementary School were not part of the
bond referendum. These improvements are being funded by a Qualified Zone
Academy Bond (QZAB), which a zero-interest loan. Mr. Maready is
overseeing the work. Mr. Maready recommended the Board award a contract
for the HVAC work to the low bidder - Diversified Construction Services,
Inc. - in the amount of $697,500.00 plus $2,200.00 for Johnson Controls.
This is a total of $699,700.
Mr. Maready recommended the Board award a contract for the electrical
work to the low bidder - Freedom Electric, Inc. - in the amount of
$89,193.
Mr. Maready recommended the Board award a contract for the roofing to
the low bidder – AAR of North Carolina, Inc. - in the amount of
$426,500.
Dr. Rick Luettich made the motion to award the bids for Beaufort Middle
Roofing to Curtis Construction in the amount of $648,075; Morehead City
Elementary School HVAC bid going to Diversified Construction Services,
Inc. in the amount of $699,700; the electrical bid to Freedom Electric,
Inc. in the amount of $89,193; and the roofing bid going to AAR of North
Carolina, Inc. in the amount of $426,500. David Carr provided the second
and the motion passed with all members voting aye.
Consider Changes to
Stanford White Associates Contracts
Mr. Maready noted
contract revisions from Stanford White Associates (SWA) were received
and reviewed. Board Attorney Neil Whitford also reviewed the contract
revisions.
Dr. Rick Luettich made the motion to approve changes to Stanford White
Associates contracts. Al Hill provided the second and the motion passed
with all members voting aye.
Consider Award of
REI Design Contract for East Carteret High School Roof
Mr. Maready said
the additional design fee to include soffit and fascia replacement at
East Carteret High School was $15,065. The design fee indicated in the
contract presented at the Board of Education’s June 13, 2006, meeting
was for $120,020. Adding the design fee for the soffit and fascia to the
roof replacement project will bring the design fee to $135,085. Dr.
Luettich clarified that these were estimates not bids and Mr. Maready
agreed.
Dr. Luettich made the motion to add the soffit and fascia design work to
the REI contract for the East Carteret High School roof. June Fulcher
provided the second and the motion passed 7-0 .
Consider Approval of
Project Ordinance Amendment Requisitions
Mr. Maready
shared Project Ordinance Amendment Requisitions with the Board. In an
effort to decrease the time between the bid and award for bond project
work, Mr. Maready recommended a format that would expedite the process.
He noted that this format would insure the county has funds in place at
bid time, and he has discussed this format with County Manager John
Langdon and gotten his approval.
Chairman Neagle asked Mr. Maready to further explain this new concept.
He explained that the Board would be asked to consider Project Ordinance
Requisitions before bids were actually received. The amount considered
would be for the budgeted amount. Once approved by the Board of
Education, Mr. Maready would request approval from the County
Commissioners. This would insure the money was available when the bids
were received. Dr. Luettich requested the Bond Construction Committee be
given an opportunity to review the concept.
Dr. Rick Luettich made the motion to approve only the Project Ordinance
Amendment Requisition for Broad Creek Middle roofing and to hold the
others until the August 8, 2006, Board meeting. Al Hill provided the
second and the motion passed 7-0.
East Carteret High
School Paving
Board members voted to remove item VII.D. Consider Bond Advisory
Committee Recommendation to Reconsider Contract to Pave ECHS Parking Lot
from the agenda.
|