February 1, 2007
School bond
projects move ahead, timeline estimates established
In November 2005, Carteret County voters approved two school
bonds totaling $50 million. These bonds were approved to address the
cost of improvements and additions to 15 school system sites.
Work is underway on many of the projects. Below is an update of
the major project work to be done by site. Additional smaller project
work will take place. If the work has been bid or started, those dates
are provided. Otherwise, an estimated timeline for that work is given.
Atlantic
Elementary School all work scheduled to be completed in
September 2007 -
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew bids
will be received January 31, 2007, approximate start in early April
2007, completed in late September 2007;
Repair leaks, replace doors and renovate kitchen hood work is
underway and will be completed by end of summer 2007;
Replace main electrical power switch bids received January 26, 2007;
work will take place during spring break April 9-13
Beaufort
Middle School all work scheduled to be completed in November
2008 -
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew bids
will be received in mid-March with estimated start date in June 2007,
completed in November 2008;
Air condition gym part of HVAC work;
Renovate kitchen hood work will take place in summer 2007;
Replace boiler deaerator part of HVAC work;
Install new roof started work September 2006, should be completed in
April 2007;
Seal soffits to eliminate untreated outside air in building
estimated start in spring 2008
Bogue
Sound Elementary School all work scheduled to be completed in
fall 2007;
Construct six classrooms bids awarded January 9, 2007 and project
underway with dirt being delivered to site, estimated completion is
August 2007;
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew bids
awarded January 9, 2007, estimated completion is August 2007;
Replace two chillers completed;
Renovate kitchen hood part of HVAC work;
Upgrade sewer system to meet State environmental requirements
estimated completion in fall 2007
Broad
Creek Middle School all work scheduled to be completed in
January 2008 -
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew bid
date in May 2007, estimated completion date in January 2008;
Install new roof work started September 2007 and estimated
completion is May 2007;
Replace two chillers completed;
Renovate kitchen hood part of HVAC work;
Upgrade sewer system to meet State environmental requirements
estimated completion in fall 2007
Croatan
High School final completion date not established -
Construct auditorium budget for 400-seat auditorium available,
exploring possibilities for funding 800-seat auditorium;
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew to be
bid June 2007, estimated completion of June 2008;
Renovate kitchen hood part of HVAC work
East
Carteret High School final completion date not established -
Construction 24-classroom/administration addition bids to be
received February 28, 2007 with estimated completion July 2008;
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew will
take place after completion of new classroom addition;
Replace existing roof bid date in May 2007 is planned with
completion expected in February 2008;
Reconfigure administration/guidance area will take place after
completion of new classroom addition;
Replace one chiller and chilled water pipe insulation chiller
replaced, insulation will take place after summer 2008;
Renovate kitchen hood part of HVAC work;
Replace windows in main building divided into three phases with
phase 1 now in process, phase 1 and 2 estimated to be completed by
December 2007, phase 3 to be completed after new classroom addition;
Repair auditorium lobby ceiling and refinish stage floor will take
place after completion of new classroom addition;
Pave parking areas and service roads will take place after
completion of new classroom addition;
Paint interior and exterior of entire school will take place after
completion of new classroom addition;
Add electrical circuits and receptacles will take place after
completion of new classroom addition;
Remove asbestos in floor, walls and ceilings will take place after
completion of new classroom addition;
Replace flooring, light fixtures and faucets will take place after
completion of new classroom addition
Harkers
Island Elementary School all work scheduled to be completed
summer 2008 -
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew bids
to be received January 31, 2007, estimated start to be early April and
completion to be late September 2007;
Air condition gym part of HVAC work;
Renovate kitchen hood part of HVAC work;
Replace
existing roof estimated to receive bids in April 2007, start
construction in June and complete in September 2007;
Recondition fuel oil tank by blasting and painting work scheduled to
take place summer 2008;
Replace windows work estimated to start October 2007 and completed
February 2008
Morehead
City Middle School all work scheduled to be completed in summer
2008 -
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew bids
to be received June 2007, start work August 2007 and complete April
2008;
Replace one chiller and chilled water insulation completed;
Renovate kitchen hood part of HVAC work;
Replace windows and ceiling tiles window work scheduled for
March-June 2008, ceiling tile work scheduled for March-May 2008;
Repair exterior walls and soffits work scheduled for March-May 2008
Morehead
City Primary School all work scheduled to be completed in fall
2008 -
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew
estimated work dates April 2008-October 2008;
Replace two chillers completed;
Renovate kitchen hood part of HVAC work;
Repair soffits and trim, cracked mortar joints estimated work start
May 2008 and finish August 2008;
Replace toilet partitions supplies ordered and work estimated to be
completed May 2007
Newport
Elementary School all work scheduled to be completed in spring
2009 -
Construct sixteen (16) classroom/administration building to receive
bids March 2007, estimate work start May 2007 and completion May 2008;
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew to
receive bids March 2007, estimate work start May 2007, completion May
2008;
Air condition gym part of HVAC work;
Replace existing roof anticipate bid date in July 2007, start work
October 2007, completion January 2008;
Reconfigure receptionist and storage areas after new building
construction completed;
Renovate kitchen hood part of HVAC work;
Replace windows in several buildings estimate work to take place
November 2008-January 2009;
Paint classroom and hall interiors and gym exterior after new
building construction completed;
Upgrade plumbing fixtures, faucets and electrical systems after new
building construction completed
Smyrna
Elementary School all work scheduled to be completed in summer
2008 -
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew to
receive bids January 31, 2007, estimated work start April and completion
October 2007;
Replace one chiller completed;
Repair roof leaks and seal wall panels work scheduled for summer
2007;
Renovate kitchen hood part of HVAC work;
Replace failing water heater and tiolet fixtures work scheduled to
take place March 2008-June 2008;
Replace windows in cafeteria work scheduled to take place October
2007-February 2008;
Upgrade sewer system to meet State environmental requirements
estimated completion in fall 2007
West
Carteret High School final completion date not established -
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew
possible start in April 2008 and completion in May 2009;
Replace existing roof over locker room and cafeteria work scheduled
to take place summer 2007;
Replace one chiller completed;
Renovate kitchen hood part of HVAC work;
Replace windows work scheduled to take place March 2008-August 2008;
Paving around school work scheduled to take place August-October
2008;
Install electronic locks and security camera at front door work
scheduled to take place September-December 2007;
Resurface track and tennis courts completed;
Install lights on softball field bids received and work scheduled to
start March 2007, completion June 2007
White
Oak Elementary School all work scheduled to be completed in
summer 2009 -
Construct sixteen (16) classroom building bids to be received March
2007, estimated start May 2007, completion July 2008;
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew bids
to be received March 2007, estimated start May 2007, completion July
2008;
Expand cafeteria eating area and kitchen bids to be received March
2007, estimated start May 2007, completion July 2008;
Expand media center bids to be received March 2007, estimated start
May 2007, completion July 2008;
Air condition gym work in process, estimated completion end March
2007;
Install new roof over campuses three brick structures - after new
building construction completed;
Replace windows work scheduled for November 2008-February 2009;
Replace faucets and tiolet fixtures - after new building construction
completed;
Upgrade main electrical power switch and intercom system work
scheduled for summer 2008;
Paint interior and exterior of school - after new building construction
completed;
Renovate kitchen hood part of HVAC work;
Pave parking lots Work scheduled for January-April 2009
Central
Services all work scheduled to be completed in summer 2009 -
Add two work bays for school bus repair work estimated start is June
2007 completion November 2007;
Replace existing roof at central office work scheduled for
February-April 2009;
Modify heating ventilation air conditioning (HVAC) system to improve
humidity control, ventilation, eliminate airborne mold/mildew at central
office work scheduled for April-June 2009
|