REPORT
BY CONSTRUCTION COMMITTEE Dr.
Luettich reported that the Construction Committee met in early December
and reviewed the bond projects budgets. The committee is made up of
Board members June Fulcher, David Carr and Dr. Luettich. Others
attending the meeting were Superintendent Dr. David Lenker, Plant
Operations Director Judson Walton, Bond Projects Manager Keith Maready
and Communications Director Tabbie Nance. Mrs.
Fulcher and Mr. Carr said they were both pleased with the status of the
bond projects and budget. Dr.
Luettich said there had been an ongoing discussion as to whether the
Board should demolish no part of the existing school, demolish Wing F,
or demolish Wing F and Wing E. Dr.
Luettich reported the Committee had developed the following
recommendation: To demolish Wings E and F and, with the savings, add an
additional four classrooms to the new classroom building. He said the
savings would be realized in new construction versus renovating an old
building. Dr. Luettich said the Committee members believe there is
enough money to build the new classrooms, and it was a better use of the
money. He added the money would be put into new construction above the
flood level and not into renovation of classrooms below the level. Mr.
Carr said his motivation was to move as many students and faculty out of
the flood plain as possible. Mr.
Maready said there would be enough savings from the demolition of Wing E
to construct the new classrooms. He said no demolition would take place
until the new classroom building is complete. Dr.
Luettich made the motion for the Board of Education to approve a plan to
demolish Wings E and F at East Carteret High School, and to design four
additional classrooms to be added to the new wing and bid as an
alternate. CONSIDER
REQUEST TO COUNTY FOR SALE OF $18.3 MILLION OF BONDS Bond
Projects Manager Keith Maready reported that to date the system has
received bids on about 6.4 percent of the $49,045,283 in bond project
work. He noted that bond projects are on scheduled at this time. Mr.
Maready noted the county has previously sold $22 million of the bond
value, which will cover the projected spending through the fourth
quarter of 2007 with the exception of the new construction at East
Carteret High School. The projected starting date for the new
construction at East Carteret High School is April 2007. Mr.
Maready asked Board members to formally request the County Commissioners
approve the sale of $18.3 million of the bonds. He noted this would
include the $4,116,675 bond for the new construction at East Carteret
High School. This will allow funds to be available for the new
construction work in April 2007 and for cash flow needs through the
third quarter of 2008. Dr.
Rick Luettich made the motion that request the County to sell $18.3
million in bond to include the new construction bonds for ECHS. Bill
Blair provided the second and all members voted aye. RECEIVE
BOND PROJECTS UPDATE Roofing
work at Beaufort Middle and Broad Creek Middle is continuing to
progress. The roofing work and HVAC work on the White Oak Elementary gym
started December 12, 2006. The roofing work should be completed during
the Christmas break. The
bids for the new construction and HVAC renovation at Bogue Sound
Elementary have been publicly advertised, and are due December 20, 2006.
The
design team and Mr. Maready are working on the East Carteret High School
sight package and plan to bid that work in late January 2007. The
first window replacement project at East Carteret High School will start
in early January 2007. Mr.
Maready plans to advertise for bids for the first major HVAC project on
December 31 with a bid date of January 31, 2007. This project will
include Atlantic Elementary, Harkers Island Elementary and Smyrna
Elementary. The
design work on new construction projects is still on schedule with bid
dates. The roof design team will have East Carteret High and Harkers
Island Elementary ready to bid in March 2007. The HVAC design team is
near completion on all HVAC work and packages will be bid throughout
2007. Work at
Morehead City Elementary School is being funded by a Qualified Zone
Academy Bond (QZAB) and is not part of the bond work. Mr. Maready
reported that the roofing, HVAC and electric work at that school are
continuing with good progress and performance. He expects to receive
bids on the Morehead City Elementary window projects January 4, 2007. |
||||||