A
special Board of Education meeting took place Wednesday, April 12, 2006,
for the purpose of reviewing the report compiled by Carteret County
Schools Construction Management Firm (Keith Maready & Associates,
LLC). The
study was conducted and reports compiled with reference to the five bond
projects involving renovations and new construction - Bogue Sound
Elementary, Croatan High auditorium, East Carteret High, Newport
Elementary and White Oak Elementary. The projects are currently under
the direction of SFL+a Architects. Keith
Maready presented the reports and indicated the study was concluded from
the following resources: three unaffiliated architectural firms; two
unaffiliated general contractors; the North Carolina Department of
Public Instruction; three Eastern North Carolina school systems with
active bond programs; and his own experience as general contractor and
construction manager. Keith
Maready indicated three possible areas for cost savings in the projects:
(1) reduction of
design fees by Carteret County Schools taking leadership of items, such
as painting, floor covering, window and door replacement and others, (2)
reduction of profits by contractors by Carteret County Schools taking
leadership of the above referenced items, and (3) reduction of inflation
rates by early performance. He
also indicated the unit costs of $146.00 per square foot for classroom
and accessory space additions are achievable, and $230.00 per square
foot is achievable for auditorium construction. These costs are
significantly less than the architectural firm’s early concept work
projections. In
summary, the bond projects scope of work can be achieved for the
approved bond value on four of the five projects, with the construction
of the auditorium at Croatan High being the exception. Study is in
process on the remainder of the bond projects.
Below is a summary of reports presented April 12 by Keith Maready
& Associates. BOGUE
SOUND ELEMENTARY SCHOOL
Approved bond value
$ 1,787,616
Projected cost to provide scope of work
$ 1,771,369
Projected Savings
$ 16,247 CROATAN
HIGH SCHOOL
Approved bond value
$ 3,320,898
Projected cost to provided scope of work
$ 4,095,445
Projected overage
$ 774,547 *Auditorium
projected cost is based on seating capacity of 560. EAST
CARTERET HIGH SCHOOL
Approved bond value (2 Bonds)
$13,412,652
Projected cost to provide scope of work
$13,129,421
Projected savings
$ 283,231 *Bond
value approved for new construction is $4,116,675 and is included in the
above. NEWPORT
ELEMENTARY SCHOOL
Approved bond value
$ 6,249,941
Projected cost to provide scope of work
$ 6,192,912
Projected savings
$ 57,029 WHITE
OAK ELEMENTARY SCHOOL
Approved bond value
$ 6,353,778
Projected cost to provide scope of work
$ 6,257,058
Projected savings
$ 96,720 *Bond
projected “New Metal Roof” with value approved at $682,044.
Value approved will not provide “New Metal Roof”; projected
cost for new metal roof is $800,000.
New sloped roof with 20 year warranty can be provided for bond
value. |
||||||